Preparing the building site for the 1st phase of the project.
Setting up profiles to give information on where the build is to be located.
Excavating footings to pour concrete footings.
Pour concrete footings.
Lay block work foundations.
Import quarried graded hardcore to infill if needed.
Set up shuttering boards to create concrete floor slab.
Set up shuttering boards for any service jointing pits if required.
Lay service ducts if required.
Lay and compact quarried 803 hardcore.
Create radon sump/s.
Lay and compact sand blinding.
Lay Visqueen radon membrane.
Lay steel work anti cracking mesh.
Pour concrete floor slab.
Dismantle shuttering boards.